News & Updates

DREAM Begins Finishing Touches at 20 Bruckner
July 20, 2022
From the lightwells to the new gymnasium, 20 Bruckner begins its final transformation phase into DREAM’s newest school. Click the photos below for a deeper look at some of the spaces.

DREAM School Leaders at 20 Bruckner
June 30, 2022
DREAM Mott Haven Elementary School Principal Jamie Platzer, DREAM Mott Haven Middle School Principal Jenn Khan, and DREAM Charter High School Principal Brandon Taylor visit what will be their schools’ new home at 20 Bruckner with DREAM co-CEOs Rich Berlin and Eve Colavito, as well as members of DREAM’s Management Team.

20 Bruckner Construction Photos
January 28, 2022
See the latest photos of construction progress at 20 Bruckner.

News

Project Timeline.

June 2019DREAM signs the lease to 20 Bruckner
December 2019Architectural designs completed
January 2020Construction kicks off
September 2020Lightwell demolition completed
November 2020Gym addition framing completed
January 2021Gym addition roof completed
January 2022Lightwell glass & skylights installation
January 2022Fifth Floor concrete pouring
January 2022Gym soundblock installation
January 2023DREAM Charter High School and Legends Team move-in
August 2023DREAM Mott Haven move-in